IMPERIA STRUCTURES LTD
NAME:IMPERIA STRUCTURES LTD
F10/100
Poor track record
Tracking 7 projects — 1 delivered, 6 still active. 5 of 7 (71%) ran late by an average of 6 months.
Delivery breakdown
How this builder's 7 tracked projects are split by outcome.
Key numbers
Total projects
7
Active
6
Completed
1
Delayed
5 (71%)
Late or overdue
Avg delay
6 mo
Worst: 6 mo
On-time rate
0%
Of completed projects
Extension rate
57%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (7)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
| Bandhan UPRERAPRJ5580 | Gautam Buddha Nagar UP | 9 Aug 2017 | — | Unknown | On track |
| Cyber UPRERAPRJ5566 | Gautam Buddha Nagar UP | 9 Aug 2017 | 31 Dec 2019 | Overdue | 78 mo overdue |
| Mirage Phase I UPRERAPRJ3142 | Gautam Buddha Nagar UP | 28 Jul 2017 | 31 Mar 2021 | Overdue | 57 mo overdue |
| Mirage Phase II UPRERAPRJ4008 | UP | 29 Jul 2017 | 31 Dec 2024 | Completed | 6 mo delay |
| Premeria UPRERAPRJ5503 | Gautam Buddha Nagar UP | 4 Aug 2017 | 31 Dec 2018 | Overdue | 90 mo overdue |
| PRIDEVILLE UPRERAPRJ545875 | Gautam Buddha Nagar UP | 1 Oct 2019 | 10 Jul 2024 | In progress | On track |
| World of Taste UPRERAPRJ6567 | Gautam Buddha Nagar UP | 31 Jul 2017 | 31 Mar 2020 | Overdue | 69 mo overdue |