MATRIX ENCLAVES PROJECTS DEV. PVT. LTD

NAME:MATRIX ENCLAVES PROJECTS DEV. PVT. LTD

Poor track record

Tracking 4 projects — 2 delivered, 2 still active. 4 of 4 (100%) ran late by an average of 12 months.

Delivery breakdown

How this builder's 4 tracked projects are split by outcome.

2 Delivered late2 Overdue

Key numbers

Total projects

4

Active

2

Completed

2

Delayed

4 (100%)

Late or overdue

Avg delay

12 mo

Worst: 12 mo

On-time rate

0%

Of completed projects

Extension rate

75%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (4)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
MARATHON NEXWORLD ELARA-1
P51700000478
Thane
MH
18 Jul 201730 Jun 2023Overdue24 mo overdue
MARATHON NEXWORLD AURA-2
P51700000507
Thane
MH
18 Jul 201730 Jun 2023Completed12 mo delay
MARATHON NEXWORLD AURA-1
P51700000652
Thane
MH
19 Jul 201730 Dec 2022Completed12 mo delay
MARATHON NEXWORLD ELARA-2
P51700000470
Thane
MH
18 Jul 201730 Dec 2024Overdue18 mo overdue