LONDON MART (PHASE-1)
UPRERAPRJ15269
Under construction
Currently within its planned build window. Watch the deadline and any new extensions.
Where this project stands
The journey from RERA registration to completion, in order.
Within the planned build window.
Registered with RERA
23 Feb 2018Original promised completion
31 Jul 2022The deadline the builder committed to at registration.
Revised deadline after extensions
3 Feb 2028Pushed back ~66 months across 3 extensions.
Today — in progress
About 19 months left until the deadline.
Timeline & delay
Key dates and how they compare to what was promised.
23 Feb 2018
When the project was registered with RERA.
31 Jul 2022
The deadline committed to at registration.
3 Feb 2028
After all approved extensions.
—
Handover date, when available.
On track0 mo
How far past deadline an ongoing project is.
3
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 31 Jul 2022 | 30 Jan 2023 | 30-01-2023 (Six months extension in view of force majeure caused by covid-19 pandemic) |
| 30 Jan 2023 | 29 Oct 2024 | — |
| 29 Oct 2024 | 3 Feb 2028 | — |
About the builder
How this developer has performed across all their tracked projects.
Strong track record
Tracking 1 project — 0 delivered, 1 still active. Limited history — read the project list before drawing conclusions.
Official records
Builder: MART PROMOTERS PVT. LTD. (NAME:MART PROMOTERS PVT. LTD.)
Data last refreshed 20 Jun 2026.