SPECTRUM METRO
UPRERAPRJ17035
Delivered — but late
This project was completed about 12 months after its original promised deadline.
Where this project stands
The journey from RERA registration to completion, in order.
Completed.
Registered with RERA
16 Jul 2018Original promised completion
1 Nov 2023The deadline the builder committed to at registration.
Revised deadline after extensions
2 Nov 2024Pushed back ~12 months across 2 extensions.
Marked completed on the portal
Shown as completed on the official registry (no exact date scraped).
Timeline & delay
Key dates and how they compare to what was promised.
16 Jul 2018
When the project was registered with RERA.
1 Nov 2023
The deadline committed to at registration.
2 Nov 2024
After all approved extensions.
—
Handover date, when available.
12 mo delay12 mo
How late the finished project was.
2
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 1 Nov 2023 | 30 Apr 2024 | 30-04-2024 (Six months extension in view of force majeure caused by covid-19 pandemic) |
| 30 Apr 2024 | 2 Nov 2024 | — |
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 6 projects — 5 delivered, 1 still active. 6 of 6 (100%) ran late by an average of 17 months.
Official records
Builder: BLUE SQUARE INFRASTRUCTURE LLP (NAME:BLUE SQUARE INFRASTRUCTURE LLP)
Data last refreshed 21 Jun 2026.