ATS KINGHOOD DRIVE
UPRERAPRJ2575
Delivered — but late
This project was completed about 6 months after its original promised deadline.
Where this project stands
The journey from RERA registration to completion, in order.
Completed.
Registered with RERA
1 Aug 2017Original promised completion
26 Oct 2022The deadline the builder committed to at registration.
Revised deadline after extensions
25 Apr 2023Pushed back ~6 months across 1 extension.
Marked completed on the portal
Shown as completed on the official registry (no exact date scraped).
Timeline & delay
Key dates and how they compare to what was promised.
1 Aug 2017
When the project was registered with RERA.
26 Oct 2022
The deadline committed to at registration.
25 Apr 2023
After all approved extensions.
—
Handover date, when available.
6 mo delay6 mo
How late the finished project was.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
38
Complaints against the builder
79
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 26 Oct 2022 | 25 Apr 2023 | 25-04-2023 (Six months extension in view of force majeure caused by covid-19 pandemic) |
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 3 projects — 2 delivered, 1 still active. 3 of 3 (100%) ran late by an average of 6 months. 79 complaints on record.