VVIP HOMES PH 2

UPRERAPRJ3977

Uttar PradeshCompleted

Delivered — but late

This project was completed about 28 months after its original promised deadline.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 31 Jul 2017Due 29 Sept 2022

Completed.

  1. Registered with RERA

    31 Jul 2017
  2. Original promised completion

    13 Jun 2020

    The deadline the builder committed to at registration.

  3. Revised deadline after extensions

    29 Sept 2022

    Pushed back ~28 months across 5 extensions.

  4. Marked completed on the portal

    Shown as completed on the official registry (no exact date scraped).

Timeline & delay

Key dates and how they compare to what was promised.

31 Jul 2017

When the project was registered with RERA.

13 Jun 2020

The deadline committed to at registration.

29 Sept 2022

After all approved extensions.

Handover date, when available.

28 mo delay27.5 mo

How late the finished project was.

5

More extensions can signal execution risk.

On UP RERA this project's registration status is Completed. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

Extension history

Each time the completion deadline was officially pushed back.

FromExtended toReason
13 Jun 202012 Dec 202012-12-2020 (Six months extension in view of force majeure caused by covid-19 pandemic)
12 Dec 202012 Jun 2021
12 Jun 202111 Dec 2021
11 Dec 202130 Jun 2022
30 Jun 202229 Sept 2022

About the builder

How this developer has performed across all their tracked projects.

Poor track record

Tracking 2 projects — 1 delivered, 1 still active. 2 of 2 (100%) ran late by an average of 28 months. Limited history — read the project list before drawing conclusions.

2 projects2 delayed (100%)0% on time

See SOLITAIRE INFRAHOME PRIVATE LIMITED's full track record →

Official records

View this project on the UP RERA portal

Builder: SOLITAIRE INFRAHOME PRIVATE LIMITED (NAME:SOLITAIRE INFRAHOME PRIVATE LIMITED)

Data last refreshed 21 Jun 2026.