← Back to search

16th Parkview - Gaur Yamuna City

UPRERAPRJ6801

Uttar PradeshCompleted

Delivered — but late

This project was completed about 27 months after its original promised deadline.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 31 Jul 2017Due 12 Feb 2025

Completed.

  1. Registered with RERA

    31 Jul 2017
  2. Original promised completion

    14 Nov 2022

    The deadline the builder committed to at registration.

  3. Revised deadline after extensions

    12 Feb 2025

    Pushed back ~27 months across 2 extensions.

  4. Marked completed on the portal

    Shown as completed on the official registry (no exact date scraped).

Timeline & delay

Key dates and how they compare to what was promised.

31 Jul 2017

When the project was registered with RERA.

14 Nov 2022

The deadline committed to at registration.

12 Feb 2025

After all approved extensions.

Handover date, when available.

27 mo delay27 mo

How late the finished project was.

2

More extensions can signal execution risk.

On UP RERA this project's registration status is Completed. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

Extension history

Each time the completion deadline was officially pushed back.

FromExtended toReason
14 Nov 202213 May 202313-05-2023 (Six months extension in view of force majeure caused by covid-19 pandemic)
13 May 202312 Feb 2025

About the builder

How this developer has performed across all their tracked projects.

Weak track record

Tracking 7 projects — 3 delivered, 4 still active. 4 of 7 (57%) ran late by an average of 9 months.

7 projects4 delayed (57%)67% on time

See GAURSONS REALTECH PRIVATE LIMITED's full track record →

Official records

View this project on the UP RERA portal

Builder: GAURSONS REALTECH PRIVATE LIMITED (NAME:GAURSONS REALTECH PRIVATE LIMITED)

Data last refreshed 21 Jun 2026.