TOWN CENTRAL - PHASE-III
UPRERAPRJ7374
Under construction
Currently within its planned build window. Watch the deadline and any new extensions.
Where this project stands
The journey from RERA registration to completion, in order.
Approaching the deadline.
Registered with RERA
1 Aug 2017Original promised completion
15 Aug 2024The deadline the builder committed to at registration.
Revised deadline after extensions
11 Nov 2026Pushed back ~27 months across 2 extensions.
Today — in progress
About 5 months left until the deadline.
Timeline & delay
Key dates and how they compare to what was promised.
1 Aug 2017
When the project was registered with RERA.
15 Aug 2024
The deadline committed to at registration.
11 Nov 2026
After all approved extensions.
—
Handover date, when available.
On track0 mo
How far past deadline an ongoing project is.
2
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 15 Aug 2024 | 14 Feb 2025 | 14-02-2025 (Six months extension in view of force majeure caused by covid-19 pandemic) |
| 14 Feb 2025 | 11 Nov 2026 | — |
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 3 projects — 1 delivered, 2 still active. 2 of 3 (67%) ran late by an average of 18 months.
Official records
Builder: PKS BUILDMART PRIVATE LIMITED (NAME:PKS BUILDMART PRIVATE LIMITED)
Data last refreshed 20 Jun 2026.