PANCHSHEEL GREENS - II (TOWER-C1 TO C4,188 VILLAS)
UPRERAPRJ8574
Delivered — but late
This project was completed about 8 months after its original promised deadline.
Where this project stands
The journey from RERA registration to completion, in order.
Completed.
Registered with RERA
12 Aug 2017Original promised completion
31 Mar 2019The deadline the builder committed to at registration.
Revised deadline after extensions
24 Nov 2019Pushed back ~8 months across 1 extension.
Marked completed on the portal
Shown as completed on the official registry (no exact date scraped).
Timeline & delay
Key dates and how they compare to what was promised.
12 Aug 2017
When the project was registered with RERA.
31 Mar 2019
The deadline committed to at registration.
24 Nov 2019
After all approved extensions.
—
Handover date, when available.
8 mo delay7.8 mo
How late the finished project was.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 31 Mar 2019 | 24 Nov 2019 | — |
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 12 projects — 11 delivered, 1 still active. 8 of 12 (67%) ran late by an average of 17 months.