AMBROSIA PHASE 04 (TOWER N1,N2,N3,N4,COMMERCIAL 5 & 6)

UPRERAPRJ888243

Uttar PradeshCompleted

Delivered — but late

This project was completed about 6 months after its original promised deadline.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 2 Jul 2019Due 14 Aug 2024

Completed.

  1. Registered with RERA

    2 Jul 2019
  2. Original promised completion

    15 Feb 2024

    The deadline the builder committed to at registration.

  3. Revised deadline after extensions

    14 Aug 2024

    Pushed back ~6 months across 1 extension.

  4. Marked completed on the portal

    Shown as completed on the official registry (no exact date scraped).

Timeline & delay

Key dates and how they compare to what was promised.

2 Jul 2019

When the project was registered with RERA.

15 Feb 2024

The deadline committed to at registration.

14 Aug 2024

After all approved extensions.

Handover date, when available.

6 mo delay6 mo

How late the finished project was.

1

More extensions can signal execution risk.

On UP RERA this project's registration status is Completed. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

Extension history

Each time the completion deadline was officially pushed back.

FromExtended toReason
15 Feb 202414 Aug 202414-08-2024 (Six months extension in view of force majeure caused by covid-19 pandemic)

About the builder

How this developer has performed across all their tracked projects.

Poor track record

Tracking 6 projects — 5 delivered, 1 still active. 6 of 6 (100%) ran late by an average of 16 months.

6 projects6 delayed (100%)0% on time

See IVR PRIME DEVELOPERS (AVADI) PRIVATE LIMITED's full track record →

Official records

View this project on the UP RERA portal

Builder: IVR PRIME DEVELOPERS (AVADI) PRIVATE LIMITED (NAME:IVR PRIME DEVELOPERS (AVADI) PRIVATE LIMITED)

Data last refreshed 21 Jun 2026.