A P PROPERTIES
RERA delivery track record · complaints · project delays
NAME:A P PROPERTIES
B76/100
Good track record
Tracking 5 projects — 5 delivered, 0 still active. 1 of 5 (20%) ran late by an average of 2 months.
Delivery breakdown
How this builder's 5 tracked projects are split by outcome.
Key numbers
Total projects
5
Active
0
Completed
5
Delayed
1 (20%)
Late or overdue
Avg delay
2.4 mo
Worst: 12 mo
On-time rate
80%
Of completed projects
Extension rate
20%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (5)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
P51800002628 Mumbai Suburban · MH | Mumbai Suburban MH | 2 Aug 2017 | 31 Mar 2025 | Completed | 12 mo delay |
P51800000737 Mumbai Suburban · MH | Mumbai Suburban MH | 23 Jul 2017 | 30 Sept 2018 | Completed | On track |
P51800032337 Mumbai Suburban · MH | Mumbai Suburban MH | 29 Dec 2021 | 31 Dec 2024 | Completed | On track |
P51800033349 Mumbai Suburban · MH | Mumbai Suburban MH | 16 Feb 2022 | 30 Jun 2024 | Completed | On track |
P51800045434 Mumbai Suburban · MH | Mumbai Suburban MH | 18 May 2022 | 31 Dec 2025 | Completed | On track |