← Back to search

AAWAM RESIDENCY PRIVATE LIMITED

NAME:AAWAM RESIDENCY

Strong track record

Tracking 4 projects — 0 delivered, 4 still active. 1 of 4 (25%) ran late.

Delivery breakdown

How this builder's 4 tracked projects are split by outcome.

1 Overdue3 In progress

Key numbers

Total projects

4

Active

4

Completed

0

Delayed

1 (25%)

Late or overdue

Avg delay

On finished projects

On-time rate

Of completed projects

Extension rate

0%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (4)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
RERA-GRG-940-2021
Gurgaon · HR
Gurgaon
HR
25 Oct 202130 Sept 2025Overdue9 mo overdue
RERA-GRG-1309-2023
Gurgaon · HR
Gurgaon
HR
12 Aug 20243 Apr 2027In progressOn track
RERA-GRG-1897-2025
Gurgaon · HR
Gurgaon
HR
21 May 202531 Mar 2029In progressOn track
RERA-GRG-2153-2026
Gurgaon · HR
Gurgaon
HR
24 Feb 202631 Jul 2030In progressOn track