ADVANCE INDIA PROJECTS LTD

NAME:ADVANCE INDIA PROJECTS

Mixed track record

Tracking 7 projects — 0 delivered, 7 still active. 4 of 7 (57%) ran late.

Delivery breakdown

How this builder's 7 tracked projects are split by outcome.

4 Overdue3 In progress

Key numbers

Total projects

7

Active

7

Completed

0

Delayed

4 (57%)

Late or overdue

Avg delay

On finished projects

On-time rate

Of completed projects

Extension rate

0%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (7)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
RERA-GRG-818-2021
Gurgaon · HR
Gurgaon
HR
10 Sept 202130 Sept 2029In progressOn track
RERA-GRG-567-2020
Gurgaon · HR
Gurgaon
HR
29 Aug 201730 Jun 2019Overdue84 mo overdue
RERA-GRG-1477-2023
Gurgaon · HR
Gurgaon
HR
2 Feb 202430 Jun 2028In progressOn track
RERA-GRG-650-2020
Gurgaon · HR
Gurgaon
HR
17 Aug 202011 May 2028In progressOn track
RERA-GRG-591-2020
Gurgaon · HR
Gurgaon
HR
3 Oct 201731 Dec 2022Overdue42 mo overdue
RERA-GRG-599-2020
Gurgaon · HR
Gurgaon
HR
28 Aug 201731 Dec 2020Overdue66 mo overdue
RERA-GRG-565-2020
Gurgaon · HR
Gurgaon
HR
18 Sept 201730 Apr 2024Overdue26 mo overdue