Alder Residency Private Limited
NAME:ALDER RESIDENCY
A100/100
Strong track record
Tracking 10 projects — 6 delivered, 4 still active. No delays recorded so far.
Delivery breakdown
How this builder's 10 tracked projects are split by outcome.
Key numbers
Total projects
10
Active
4
Completed
6
Delayed
0 (0%)
Late or overdue
Avg delay
0 mo
On finished projects
On-time rate
100%
Of completed projects
Extension rate
0%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (10)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
P51800045360 Mumbai Suburban · MH | Mumbai Suburban MH | 18 May 2022 | 31 Mar 2028 | Completed | On track |
P51800045409 Mumbai Suburban · MH | Mumbai Suburban MH | 18 May 2022 | 31 Mar 2028 | Completed | On track |
P51800034531 Mumbai Suburban · MH | Mumbai Suburban MH | 11 Apr 2022 | 31 Mar 2028 | Completed | On track |
P51800047621 Mumbai Suburban · MH | Mumbai Suburban MH | 14 Nov 2022 | 30 Jun 2028 | Completed | On track |
P51800047620 Mumbai Suburban · MH | Mumbai Suburban MH | 14 Nov 2022 | 30 Jun 2028 | Completed | On track |
P51800051328 Mumbai Suburban · MH | Mumbai Suburban MH | 8 Jun 2023 | 31 Dec 2028 | In progress | On track |
P51800051153 Mumbai Suburban · MH | Mumbai Suburban MH | 1 Jun 2023 | 31 Dec 2028 | Completed | On track |
P51800053558 Mumbai Suburban · MH | Mumbai Suburban MH | 10 Nov 2023 | 31 Dec 2028 | In progress | On track |
P51800053828 Mumbai Suburban · MH | Mumbai Suburban MH | 1 Dec 2023 | 31 Dec 2028 | In progress | On track |
P51800077538 Mumbai Suburban · MH | Mumbai Suburban MH | 20 Aug 2024 | 30 Jun 2029 | In progress | On track |