AVARNA PROJECTS LLP
NAME:AVARNA PROJECTS
C60/100
Mixed track record
Tracking 6 projects — 0 delivered, 6 still active. 3 of 6 (50%) ran late.
Delivery breakdown
How this builder's 6 tracked projects are split by outcome.
Key numbers
Total projects
6
Active
6
Completed
0
Delayed
3 (50%)
Late or overdue
Avg delay
—
On finished projects
On-time rate
—
Of completed projects
Extension rate
0%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (6)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
RERA-GRG-1233-2022 Gurgaon · HR | Gurgaon HR | 23 Jan 2023 | 30 Apr 2027 | In progress | On track |
RERA-GRG-1829-2024 Gurgaon · HR | Gurgaon HR | 5 Feb 2025 | 30 Apr 2030 | In progress | On track |
RERA-GRG-1011-2022 Gurgaon · HR | Gurgaon HR | 25 Apr 2022 | 29 Dec 2025 | Overdue | 6 mo overdue |
RERA-GRG-1012-2022 Gurgaon · HR | Gurgaon HR | 27 Jul 2022 | 31 Dec 2026 | In progress | On track |
RERA-GRG-499-2019 Gurgaon · HR | Gurgaon HR | 27 Jan 2020 | 30 Jun 2024 | Overdue | 24 mo overdue |
RERA-GRG-505-2019 Gurgaon · HR | Gurgaon HR | 27 Jan 2020 | 30 Dec 2025 | Overdue | 6 mo overdue |