BHAGWATI DEVELOPERS

RERA delivery track record · complaints · project delays

NAME:BHAGWATI DEVELOPERS

Good track record

Tracking 7 projects — 6 delivered, 1 still active. 2 of 7 (29%) ran late by an average of 3 months.

Delivery breakdown

How this builder's 7 tracked projects are split by outcome.

5 Delivered on time1 Delivered late1 Overdue

Key numbers

Total projects

7

Active

1

Completed

6

Delayed

2 (29%)

Late or overdue

Avg delay

3 mo

Worst: 18 mo

On-time rate

83%

Of completed projects

Extension rate

29%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (7)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
P52000004807
Raigarh · MH
Raigarh
MH
9 Aug 201731 Dec 2018CompletedOn track
P51700003864
Thane · MH
Thane
MH
6 Aug 201731 Dec 2018CompletedOn track
P52000003952
Raigarh · MH
Raigarh
MH
7 Aug 201730 Jun 2023Completed18 mo delay
P52000006596
Raigarh · MH
Raigarh
MH
14 Aug 201730 Jun 2023Overdue18 mo overdue
P52000006873
Raigarh · MH
Raigarh
MH
16 Aug 201731 Dec 2019CompletedOn track
P52000009560
Raigarh · MH
Raigarh
MH
22 Aug 201731 Dec 2018CompletedOn track
P52000011622
Raigarh · MH
Raigarh
MH
31 Aug 201731 Dec 2018CompletedOn track