BHOLENATH DEVELOPERS LTD.
RERA delivery track record · complaints · project delays
NAME:BHOLENATH DEVELOPERS
F10/100
Poor track record
Tracking 4 projects — 4 delivered, 0 still active. 3 of 4 (75%) ran late by an average of 26 months.
Delivery breakdown
How this builder's 4 tracked projects are split by outcome.
Key numbers
Total projects
4
Active
0
Completed
4
Delayed
3 (75%)
Late or overdue
Avg delay
26 mo
Worst: 62 mo
On-time rate
25%
Of completed projects
Extension rate
75%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (4)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
P51800004835 Mumbai Suburban · MH | Mumbai Suburban MH | 9 Aug 2017 | 14 Nov 2022 | Completed | 12 mo delay |
P51800009179 Mumbai Suburban · MH | Mumbai Suburban MH | 19 Aug 2017 | 31 Oct 2018 | Completed | 62 mo delay |
P51800000759 Mumbai Suburban · MH | Mumbai Suburban MH | 23 Jul 2017 | 30 Jun 2018 | Completed | 30 mo delay |
P51800002227 Mumbai Suburban · MH | Mumbai Suburban MH | 31 Jul 2017 | 31 Mar 2018 | Completed | On track |