DISHA CONSTRUCTION

RERA delivery track record · complaints · project delays

NAME:DISHA CONSTRUCTION

Poor track record

Tracking 4 projects — 4 delivered, 0 still active. 3 of 4 (75%) ran late by an average of 24 months.

Delivery breakdown

How this builder's 4 tracked projects are split by outcome.

1 Delivered on time3 Delivered late

Key numbers

Total projects

4

Active

0

Completed

4

Delayed

3 (75%)

Late or overdue

Avg delay

24 mo

Worst: 48 mo

On-time rate

25%

Of completed projects

Extension rate

75%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (4)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
P51800002197
Mumbai Suburban · MH
Mumbai Suburban
MH
31 Jul 201731 Dec 2019Completed48 mo delay
P51800001236
Mumbai Suburban · MH
Mumbai Suburban
MH
27 Jul 201731 Dec 2019Completed24 mo delay
P51800001640
Mumbai Suburban · MH
Mumbai Suburban
MH
29 Jul 201731 Mar 2020Completed24 mo delay
P51800024339
Mumbai Suburban · MH
Mumbai Suburban
MH
5 Feb 202030 Jan 2025CompletedOn track