ELAN LIMITED

NAME:ELAN

Weak track record

Tracking 4 projects — 0 delivered, 4 still active. 3 of 4 (75%) ran late.

Delivery breakdown

How this builder's 4 tracked projects are split by outcome.

3 Overdue1 In progress

Key numbers

Total projects

4

Active

4

Completed

0

Delayed

3 (75%)

Late or overdue

Avg delay

On finished projects

On-time rate

Of completed projects

Extension rate

0%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (4)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
RERA-GRG-398-2019
Gurgaon · HR
Gurgaon
HR
14 Sept 201713 Sept 2022Overdue45 mo overdue
RERA-GRG-102-2018
Gurgaon · HR
Gurgaon
HR
6 Dec 201831 Dec 2023Overdue30 mo overdue
ELAN PARADISESame name
RERA-GRG-813-2021
Gurgaon · HR
Gurgaon
HR
22 Mar 202130 Sept 2025Overdue9 mo overdue
ELAN PARADISESame name
RERA-GRG-1062-2022
Gurgaon · HR
Gurgaon
HR
4 Jul 202216 Jun 2027In progressOn track