Enerrgia Skyi Developers
NAME:ENERRGIA SKYI DEVELOPERS
F10/100
Poor track record
Tracking 4 projects — 4 delivered, 0 still active. 3 of 4 (75%) ran late by an average of 18 months.
Delivery breakdown
How this builder's 4 tracked projects are split by outcome.
Key numbers
Total projects
4
Active
0
Completed
4
Delayed
3 (75%)
Late or overdue
Avg delay
18.3 mo
Worst: 37 mo
On-time rate
25%
Of completed projects
Extension rate
75%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (4)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
P52100000769 Pune · MH | Pune MH | 23 Jul 2017 | 31 Dec 2018 | Completed | On track |
P52100001117 Pune · MH | Pune MH | 26 Jul 2017 | 30 Nov 2020 | Completed | 18 mo delay |
P52100000805 Pune · MH | Pune MH | 23 Jul 2017 | 30 Nov 2020 | Completed | 37 mo delay |
P52100000764 Pune · MH | Pune MH | 23 Jul 2017 | 30 Nov 2020 | Completed | 18 mo delay |