Growmore Space Solutions Private Limited
NAME:GROWMORE SPACE SOLUTIONS
B71/100
Good track record
Tracking 4 projects — 4 delivered, 0 still active. 1 of 4 (25%) ran late by an average of 3 months.
Delivery breakdown
How this builder's 4 tracked projects are split by outcome.
Key numbers
Total projects
4
Active
0
Completed
4
Delayed
1 (25%)
Late or overdue
Avg delay
3 mo
Worst: 12 mo
On-time rate
75%
Of completed projects
Extension rate
25%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (4)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
P51800005958 Mumbai Suburban · MH | Mumbai Suburban MH | 14 Aug 2017 | 31 Dec 2019 | Completed | On track |
P51800029432 Mumbai Suburban · MH | Mumbai Suburban MH | 29 May 2021 | 30 Jun 2023 | Completed | On track |
P51800033556 Mumbai Suburban · MH | Mumbai Suburban MH | 22 Feb 2022 | 31 Dec 2024 | Completed | 12 mo delay |
P51800033488 Mumbai Suburban · MH | Mumbai Suburban MH | 22 Feb 2022 | 31 Dec 2024 | Completed | On track |