Indu Enterprise
RERA delivery track record · complaints · project delays
NAME:INDU ENTERPRISE
F26/100
Poor track record
Tracking 3 projects — 2 delivered, 1 still active. 2 of 3 (67%) ran late by an average of 24 months.
Delivery breakdown
How this builder's 3 tracked projects are split by outcome.
Key numbers
Total projects
3
Active
1
Completed
2
Delayed
2 (67%)
Late or overdue
Avg delay
23.5 mo
Worst: 47 mo
On-time rate
50%
Of completed projects
Extension rate
67%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (3)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
P51800006110 Mumbai Suburban · MH | Mumbai Suburban MH | 14 Aug 2017 | 31 Dec 2018 | Completed | 47 mo delay |
P51800011080 Mumbai Suburban · MH | Mumbai Suburban MH | 31 Aug 2017 | 31 Dec 2020 | Completed | On track |
P51800002668 Mumbai Suburban · MH | Mumbai Suburban MH | 2 Aug 2017 | 31 May 2020 | Overdue | 11 mo overdue |