Joyville Shapoorji Housing Private Limited

RERA delivery track record · complaints · project delays

NAME:JOYVILLE SHAPOORJI HOUSING

Good track record

Tracking 8 projects — 1 delivered, 7 still active. 6 of 8 (75%) ran late.

Delivery breakdown

How this builder's 8 tracked projects are split by outcome.

1 Delivered on time6 Overdue1 In progress

Key numbers

Total projects

8

Active

7

Completed

1

Delayed

6 (75%)

Late or overdue

Avg delay

0 mo

On finished projects

On-time rate

100%

Of completed projects

Extension rate

0%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (8)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
RERA-GRG-75-2018
Gurgaon · HR
Gurgaon
HR
29 Nov 201815 Mar 2023Overdue39 mo overdue
RERA-GRG-82-2018
Gurgaon · HR
Gurgaon
HR
29 Nov 201815 Sept 2023Overdue33 mo overdue
RERA-GRG-211-2019
Gurgaon · HR
Gurgaon
HR
24 May 201930 Apr 2024Overdue26 mo overdue
RERA-GRG-213-2019
Gurgaon · HR
Gurgaon
HR
24 May 201931 Dec 2024Overdue18 mo overdue
RERA-GRG-781-2020
Gurgaon · HR
Gurgaon
HR
8 Jan 202131 Jul 2025Overdue11 mo overdue
RERA-GRG-236-2019
Gurgaon · HR
Gurgaon
HR
6 Sept 201931 Dec 2024Overdue18 mo overdue
P52100054174
Pune · MH
Pune
MH
1 Jan 202431 Dec 2027In progressOn track
P51900030420
Mumbai City · MH
Mumbai City
MH
25 Aug 202130 Sept 2022CompletedOn track