KUM KUM ENTERPRISES
RERA delivery track record · complaints · project delays
NAME:KUM KUM ENTERPRISES
F13/100
Poor track record
Tracking 2 projects — 1 delivered, 1 still active. 1 of 2 (50%) ran late by an average of 18 months. Limited history — read the project list before drawing conclusions.
This builder has only 2 tracked projects in our coverage area, so the grade is based on a small sample. Read the project list below before drawing conclusions.
Delivery breakdown
How this builder's 2 tracked projects are split by outcome.
Key numbers
Total projects
2
Active
1
Completed
1
Delayed
1 (50%)
Late or overdue
Avg delay
18 mo
Worst: 18 mo
On-time rate
0%
Of completed projects
Extension rate
50%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (2)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
P52000009221 Raigarh · MH | Raigarh MH | 22 Aug 2017 | 31 Mar 2019 | Completed | 18 mo delay |
P51800053127 Mumbai Suburban · MH | Mumbai Suburban MH | 16 Oct 2023 | 31 Dec 2026 | In progress | On track |