Lashkaria Housing & infrastructure Limited
NAME:LASHKARIA HOUSING INFRASTRUCTURE
D44/100
Weak track record
Tracking 4 projects — 2 delivered, 2 still active. 1 of 4 (25%) ran late by an average of 23 months.
Delivery breakdown
How this builder's 4 tracked projects are split by outcome.
Key numbers
Total projects
4
Active
2
Completed
2
Delayed
1 (25%)
Late or overdue
Avg delay
23.2 mo
Worst: 46.4 mo
On-time rate
50%
Of completed projects
Extension rate
50%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (4)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
P51800008422 Mumbai Suburban · MH | Mumbai Suburban MH | 18 Aug 2017 | 1 Aug 2019 | Completed | On track |
P51800010789 Mumbai Suburban · MH | Mumbai Suburban MH | 31 Aug 2017 | 30 Jun 2019 | Completed | 46 mo delay |
P51800023377 Mumbai Suburban · MH | Mumbai Suburban MH | 12 Dec 2019 | 1 Nov 2025 | In progress | On track |
P51800052471 Mumbai Suburban · MH | Mumbai Suburban MH | 8 Sept 2023 | 31 Dec 2028 | In progress | On track |