M/s. Earth Graphics

RERA delivery track record · complaints · project delays

NAME:M S EARTH GRAPHICS

Poor track record

Tracking 3 projects — 2 delivered, 1 still active. 3 of 3 (100%) ran late by an average of 31 months.

Delivery breakdown

How this builder's 3 tracked projects are split by outcome.

2 Delivered late1 Overdue

Key numbers

Total projects

3

Active

1

Completed

2

Delayed

3 (100%)

Late or overdue

Avg delay

31.5 mo

Worst: 39 mo

On-time rate

0%

Of completed projects

Extension rate

100%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (3)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
P51900004900
Mumbai Suburban · MH
Mumbai Suburban
MH
9 Aug 201731 Dec 2019Completed24 mo delay
P51900008314
Mumbai City · MH
Mumbai City
MH
18 Aug 201719 Jun 2021Completed39 mo delay
P51900021985
Mumbai City · MH
Mumbai City
MH
25 Aug 201922 Dec 2023Overdue30 mo overdue