MAA SANKALP BUILDCON
NAME:MAA SANKALP BUILDCON
F0/100
Poor track record
Tracking 4 projects — 4 delivered, 0 still active. 4 of 4 (100%) ran late by an average of 43 months.
Delivery breakdown
How this builder's 4 tracked projects are split by outcome.
Key numbers
Total projects
4
Active
0
Completed
4
Delayed
4 (100%)
Late or overdue
Avg delay
42.8 mo
Worst: 60 mo
On-time rate
0%
Of completed projects
Extension rate
100%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (4)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
P52100009316 Pune · MH | Pune MH | 22 Aug 2017 | 31 Dec 2018 | Completed | 60 mo delay |
P52100011408 Pune · MH | Pune MH | 31 Aug 2017 | 31 Dec 2019 | Completed | 48 mo delay |
P52100004883 Pune · MH | Pune MH | 9 Aug 2017 | 31 Dec 2019 | Completed | 51 mo delay |
P52100003592 Pune · MH | Pune MH | 5 Aug 2017 | 30 Sept 2018 | Completed | 12 mo delay |