MACROTECH DEVELOPERS LIMITED
RERA delivery track record · complaints · project delays
NAME:MACROTECH DEVELOPERS
A86/100
Strong track record
Tracking 9 projects — 9 delivered, 0 still active. 1 of 9 (11%) ran late by an average of 2 months.
Delivery breakdown
How this builder's 9 tracked projects are split by outcome.
Key numbers
Total projects
9
Active
0
Completed
9
Delayed
1 (11%)
Late or overdue
Avg delay
1.9 mo
Worst: 16.9 mo
On-time rate
89%
Of completed projects
Extension rate
11%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (9)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
P51800014891 Mumbai Suburban · MH | Mumbai Suburban MH | 9 Jan 2018 | 31 Jul 2023 | Completed | On track |
P51800014860 Mumbai Suburban · MH | Mumbai Suburban MH | 8 Jan 2018 | 31 Jul 2023 | Completed | On track |
P51800014869 Mumbai Suburban · MH | Mumbai Suburban MH | 8 Jan 2018 | 30 Oct 2023 | Completed | On track |
P51900008345 Mumbai City · MH | Mumbai City MH | 18 Aug 2017 | 30 Sept 2018 | Completed | 17 mo delay |
P51900010326 Mumbai City · MH | Mumbai City MH | 24 Aug 2017 | 30 Dec 2022 | Completed | On track |
P51900008962 Mumbai City · MH | Mumbai City MH | 19 Aug 2017 | 30 Jun 2021 | Completed | On track |
P51900014910 Mumbai City · MH | Mumbai City MH | 11 Jan 2018 | 30 Oct 2023 | Completed | On track |
P51900014984 Mumbai City · MH | Mumbai City MH | 15 Jan 2018 | 30 Mar 2023 | Completed | On track |
P51800016528 Mumbai Suburban · MH | Mumbai Suburban MH | 21 May 2018 | 28 Aug 2023 | Completed | On track |