Mahindra Lifespace Developers limited

NAME:MAHINDRA LIFESPACE DEVELOPERS

Strong track record

Tracking 8 projects — 4 delivered, 4 still active. 1 of 8 (13%) ran late.

Delivery breakdown

How this builder's 8 tracked projects are split by outcome.

4 Delivered on time1 Overdue3 In progress

Key numbers

Total projects

8

Active

4

Completed

4

Delayed

1 (13%)

Late or overdue

Avg delay

0 mo

On finished projects

On-time rate

100%

Of completed projects

Extension rate

0%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (8)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
P51800016833
Mumbai Suburban · MH
Mumbai Suburban
MH
18 Jun 201830 Sept 2023CompletedOn track
P51800022126
Mumbai Suburban · MH
Mumbai Suburban
MH
28 Aug 201930 Mar 2025CompletedOn track
P51800022067
Mumbai Suburban · MH
Mumbai Suburban
MH
25 Aug 201930 Mar 2025CompletedOn track
P51800028352
Mumbai Suburban · MH
Mumbai Suburban
MH
18 Feb 202130 Jun 2026In progressOn track
P51800031699
Mumbai Suburban · MH
Mumbai Suburban
MH
8 Nov 202131 Dec 2025Overdue6 mo overdue
P51800033573
Mumbai Suburban · MH
Mumbai Suburban
MH
22 Feb 202230 Jun 2026In progressOn track
P51800033415
Mumbai Suburban · MH
Mumbai Suburban
MH
22 Feb 202231 Jul 2025CompletedOn track
P51800054671
Mumbai Suburban · MH
Mumbai Suburban
MH
2 Feb 202431 Dec 2029In progressOn track