MANTHAN DEVELOPMENT CORPORATION

RERA delivery track record · complaints · project delays

NAME:MANTHAN DEVELOPMENT

Poor track record

Tracking 3 projects — 2 delivered, 1 still active. 2 of 3 (67%) ran late by an average of 36 months.

Delivery breakdown

How this builder's 3 tracked projects are split by outcome.

2 Delivered late1 In progress

Key numbers

Total projects

3

Active

1

Completed

2

Delayed

2 (67%)

Late or overdue

Avg delay

36 mo

Worst: 48 mo

On-time rate

0%

Of completed projects

Extension rate

67%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (3)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
P51800005360
Mumbai Suburban · MH
Mumbai Suburban
MH
11 Aug 201730 Dec 2027In progressOn track
P51800015626
Mumbai Suburban · MH
Mumbai Suburban
MH
15 Mar 201830 Dec 2022Completed48 mo delay
P51800004366
Mumbai Suburban · MH
Mumbai Suburban
MH
9 Aug 201730 Dec 2024Completed24 mo delay