MARVEL LANDMARKS PVT LTD

NAME:MARVEL LANDMARKS

Mixed track record

Tracking 6 projects — 5 delivered, 1 still active. 2 of 6 (33%) ran late by an average of 6 months.

Delivery breakdown

How this builder's 6 tracked projects are split by outcome.

3 Delivered on time2 Delivered late1 In progress

Key numbers

Total projects

6

Active

1

Completed

5

Delayed

2 (33%)

Late or overdue

Avg delay

6 mo

Worst: 18 mo

On-time rate

60%

Of completed projects

Extension rate

50%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (6)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
P52100001843
Pune · MH
Pune
MH
29 Jul 201730 Jun 2021In progressOn track
P52100002064
Pune · MH
Pune
MH
31 Jul 201731 Mar 2018CompletedOn track
P52100002371
Pune · MH
Pune
MH
31 Jul 201731 Dec 2018Completed12 mo delay
P52100002514
Pune · MH
Pune
MH
1 Aug 201730 Jun 2019Completed18 mo delay
P52100001815
Pune · MH
Pune
MH
29 Jul 201731 Dec 2019CompletedOn track
P52100010976
Pune · MH
Pune
MH
31 Aug 201731 Jul 2018CompletedOn track