MAVERICK REALTORS
RERA delivery track record · complaints · project delays
NAME:MAVERICK REALTORS
F20/100
Poor track record
Tracking 9 projects — 2 delivered, 7 still active. 7 of 9 (78%) ran late by an average of 14 months.
Delivery breakdown
How this builder's 9 tracked projects are split by outcome.
Key numbers
Total projects
9
Active
7
Completed
2
Delayed
7 (78%)
Late or overdue
Avg delay
14 mo
Worst: 28 mo
On-time rate
50%
Of completed projects
Extension rate
78%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (9)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
P51800012145 Mumbai Suburban · MH | Mumbai Suburban MH | 1 Sept 2017 | 30 Jun 2021 | Completed | 28 mo delay |
P51800008649 Mumbai Suburban · MH | Mumbai Suburban MH | 19 Aug 2017 | 31 Dec 2019 | Overdue | 32 mo overdue |
P51800003411 Mumbai Suburban · MH | Mumbai Suburban MH | 5 Aug 2017 | 30 Jun 2021 | Overdue | 32 mo overdue |
P51800005187 Mumbai Suburban · MH | Mumbai Suburban MH | 10 Aug 2017 | 30 Jun 2021 | Overdue | 32 mo overdue |
P51800003963 Mumbai Suburban · MH | Mumbai Suburban MH | 7 Aug 2017 | 30 Dec 2022 | Overdue | On track |
P51800007273 Mumbai Suburban · MH | Mumbai Suburban MH | 17 Aug 2017 | 31 Dec 2018 | Overdue | 18 mo overdue |
P51800029133 Mumbai Suburban · MH | Mumbai Suburban MH | 29 Apr 2021 | 31 Mar 2025 | Completed | On track |
P51800029136 Mumbai Suburban · MH | Mumbai Suburban MH | 29 Apr 2021 | 31 Mar 2025 | Overdue | 3 mo overdue |
P51800046693 Mumbai Suburban · MH | Mumbai Suburban MH | 29 Aug 2022 | 31 Mar 2026 | Overdue | 3 mo overdue |