PANOM DEVELOPERS LLP
RERA delivery track record · complaints · project delays
NAME:PANOM DEVELOPERS
B66/100
Good track record
Tracking 5 projects — 4 delivered, 1 still active. 2 of 5 (40%) ran late by an average of 3 months.
Delivery breakdown
How this builder's 5 tracked projects are split by outcome.
Key numbers
Total projects
5
Active
1
Completed
4
Delayed
2 (40%)
Late or overdue
Avg delay
3 mo
Worst: 12 mo
On-time rate
75%
Of completed projects
Extension rate
20%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (5)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
P51800017635 Mumbai Suburban · MH | Mumbai Suburban MH | 29 Aug 2018 | 31 Dec 2019 | Completed | On track |
P51800029092 Mumbai Suburban · MH | Mumbai Suburban MH | 26 Apr 2021 | 28 Feb 2023 | Completed | On track |
P51800033652 Mumbai Suburban · MH | Mumbai Suburban MH | 2 Mar 2022 | 30 Jun 2024 | Completed | 12 mo delay |
P51800049682 Mumbai Suburban · MH | Mumbai Suburban MH | 22 Feb 2023 | 31 Dec 2025 | Overdue | 6 mo overdue |
P51800005027 Mumbai Suburban · MH | Mumbai Suburban MH | 9 Aug 2017 | 31 Dec 2019 | Completed | On track |