PARANJAPE SCHEMES (CONSTRUCTION) LTD
NAME:PARANJAPE SCHEMES CONSTRUCTION
F29/100
Poor track record
Tracking 9 projects — 9 delivered, 0 still active. 5 of 9 (56%) ran late by an average of 20 months.
Delivery breakdown
How this builder's 9 tracked projects are split by outcome.
Key numbers
Total projects
9
Active
0
Completed
9
Delayed
5 (56%)
Late or overdue
Avg delay
19.7 mo
Worst: 59.9 mo
On-time rate
44%
Of completed projects
Extension rate
56%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (9)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
P52100000035 Pune · MH | Pune MH | 16 Jun 2017 | 31 Mar 2019 | Completed | 18 mo delay |
P52100000029 Pune · MH | Pune MH | 13 Jun 2017 | 31 Jul 2022 | Completed | 24 mo delay |
P52100000054 Pune · MH | Pune MH | 19 Jun 2017 | 31 Dec 2018 | Completed | On track |
P52100000060 Pune · MH | Pune MH | 22 Jun 2017 | 30 Dec 2022 | Completed | On track |
P52100000066 Pune · MH | Pune MH | 22 Jun 2017 | 31 Mar 2018 | Completed | On track |
P52100000067 Pune · MH | Pune MH | 22 Jun 2017 | 30 Dec 2022 | Completed | 24 mo delay |
P52100000241 Pune · MH | Pune MH | 10 Jul 2017 | 30 Sept 2020 | Completed | On track |
P52100000452 Pune · MH | Pune MH | 18 Jul 2017 | 31 Dec 2020 | Completed | 51 mo delay |
P52100000303 Pune · MH | Pune MH | 15 Jul 2017 | 31 Mar 2020 | Completed | 60 mo delay |