PRASAD ESTATE

RERA delivery track record · complaints · project delays

NAME:PRASAD ESTATE

Weak track record

Tracking 2 projects — 2 delivered, 0 still active. 1 of 2 (50%) ran late by an average of 15 months. Limited history — read the project list before drawing conclusions.

This builder has only 2 tracked projects in our coverage area, so the grade is based on a small sample. Read the project list below before drawing conclusions.

Delivery breakdown

How this builder's 2 tracked projects are split by outcome.

1 Delivered on time1 Delivered late

Key numbers

Total projects

2

Active

0

Completed

2

Delayed

1 (50%)

Late or overdue

Avg delay

15 mo

Worst: 30 mo

On-time rate

50%

Of completed projects

Extension rate

50%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (2)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
P52000006076
Raigarh · MH
Raigarh
MH
14 Aug 201731 Oct 2018CompletedOn track
P52000007874
Raigarh · MH
Raigarh
MH
18 Aug 201730 Sept 2019Completed30 mo delay