RPS INFRASTRUCTURE LTD

NAME:RPS INFRASTRUCTURE

Poor track record

Tracking 8 projects — 0 delivered, 8 still active. 7 of 8 (88%) ran late.

Delivery breakdown

How this builder's 8 tracked projects are split by outcome.

7 Overdue1 In progress

Key numbers

Total projects

8

Active

8

Completed

0

Delayed

7 (88%)

Late or overdue

Avg delay

On finished projects

On-time rate

Of completed projects

Extension rate

0%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (8)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
RERA-PKL-615-2019
Faridabad · HR
Faridabad
HR
15 Sept 201714 Jun 2023Overdue36 mo overdue
RERA-PKL-624-2019
Faridabad · HR
Faridabad
HR
15 Sept 201714 Jun 2025Overdue12 mo overdue
RERA-PKL-747-2019
Faridabad · HR
Faridabad
HR
15 Sept 201714 Sept 2023Overdue33 mo overdue
RERA-PKL-333-2018
Faridabad · HR
Faridabad
HR
15 Sept 201714 Jun 2024Overdue24 mo overdue
RERA-PKL-1708-2025
Faridabad · HR
Faridabad
HR
31 Mar 2029In progressOn track
RERA-PKL-338-2018
Faridabad · HR
Faridabad
HR
15 Sept 201714 Jun 2024Overdue24 mo overdue
RERA-PKL-336-2018
Faridabad · HR
Faridabad
HR
15 Sept 201714 Jun 2024Overdue24 mo overdue
RERA-PKL-512-2019
Faridabad · HR
Faridabad
HR
31 Oct 2024Overdue20 mo overdue