Runwal Construction Private Limited

RERA delivery track record · complaints · project delays

NAME:RUNWAL CONSTRUCTION

Poor track record

Tracking 6 projects — 3 delivered, 3 still active. 3 of 6 (50%) ran late by an average of 26 months.

Delivery breakdown

How this builder's 6 tracked projects are split by outcome.

1 Delivered on time2 Delivered late2 Overdue1 In progress

Key numbers

Total projects

6

Active

3

Completed

3

Delayed

3 (50%)

Late or overdue

Avg delay

26.3 mo

Worst: 67 mo

On-time rate

33%

Of completed projects

Extension rate

33%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (6)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
P51800012621
Mumbai Suburban · MH
Mumbai Suburban
MH
6 Sept 201731 Jul 2028CompletedOn track
P51800025926
Mumbai Suburban · MH
Mumbai Suburban
MH
31 Jul 202030 Jun 2026OverdueOn track
P51800029440
Mumbai Suburban · MH
Mumbai Suburban
MH
29 May 202131 Mar 2026Overdue3 mo overdue
P51800032538
Mumbai Suburban · MH
Mumbai Suburban
MH
10 Jan 202231 Mar 2027In progressOn track
P51700001383
Thane · MH
Thane
MH
27 Jul 201731 May 2019Completed67 mo delay
P51800000347
Mumbai Suburban · MH
Mumbai Suburban
MH
15 Jul 201731 May 2018Completed12 mo delay