SHRADDHA LANDMARK PRIVATE LIMITED
RERA delivery track record · complaints · project delays
NAME:SHRADDHA LANDMARK
B72/100
Good track record
Tracking 20 projects — 11 delivered, 9 still active. 3 of 20 (15%) ran late by an average of 2 months.
Delivery breakdown
How this builder's 20 tracked projects are split by outcome.
Key numbers
Total projects
20
Active
9
Completed
11
Delayed
3 (15%)
Late or overdue
Avg delay
2.2 mo
Worst: 19.9 mo
On-time rate
73%
Of completed projects
Extension rate
35%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (20)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
P51800012384 Mumbai Suburban · MH | Mumbai Suburban MH | 1 Sept 2017 | 31 Dec 2017 | Completed | 3 mo delay |
P51800008864 Mumbai Suburban · MH | Mumbai Suburban MH | 19 Aug 2017 | 30 Dec 2023 | In progress | On track |
P51800010938 Mumbai Suburban · MH | Mumbai Suburban MH | 31 Aug 2017 | 31 Dec 2018 | Completed | 20 mo delay |
P51800021833 Mumbai Suburban · MH | Mumbai Suburban MH | 31 Jul 2019 | 30 Dec 2024 | Completed | On track |
P51800021957 Mumbai Suburban · MH | Mumbai Suburban MH | 25 Aug 2019 | 30 Dec 2024 | Completed | On track |
P51800024932 Mumbai Suburban · MH | Mumbai Suburban MH | 12 Mar 2020 | 30 Dec 2024 | Completed | On track |
P51800024933 Mumbai Suburban · MH | Mumbai Suburban MH | 12 Mar 2020 | 30 Dec 2024 | Completed | On track |
P51800027842 Mumbai Suburban · MH | Mumbai Suburban MH | 8 Jan 2021 | 30 Jun 2024 | Completed | On track |
P51800028400 Mumbai Suburban · MH | Mumbai Suburban MH | 2 Mar 2021 | 30 Jun 2026 | In progress | On track |
P51800028936 Mumbai Suburban · MH | Mumbai Suburban MH | 15 Apr 2021 | 31 Dec 2027 | In progress | On track |
P51800033921 Mumbai Suburban · MH | Mumbai Suburban MH | 14 Mar 2022 | 31 Dec 2025 | Completed | On track |
P51800045620 Mumbai Suburban · MH | Mumbai Suburban MH | 26 May 2022 | 30 Apr 2024 | Completed | 1 mo delay |
P51800046232 Mumbai Suburban · MH | Mumbai Suburban MH | 20 Jun 2022 | 31 Dec 2025 | In progress | On track |
P51800046277 Mumbai Suburban · MH | Mumbai Suburban MH | 20 Jun 2022 | 31 Dec 2025 | Completed | On track |
P51800046124 Mumbai Suburban · MH | Mumbai Suburban MH | 20 Jun 2022 | 31 Dec 2025 | Completed | On track |
P51800050356 Mumbai Suburban · MH | Mumbai Suburban MH | 5 Apr 2023 | 31 Dec 2026 | In progress | On track |
P51800051741 Mumbai Suburban · MH | Mumbai Suburban MH | 27 Jun 2023 | 31 May 2026 | In progress | On track |
P51800054815 Mumbai Suburban · MH | Mumbai Suburban MH | 12 Feb 2024 | 31 May 2028 | In progress | On track |
P51800056282 Mumbai Suburban · MH | Mumbai Suburban MH | 22 May 2024 | 30 Jun 2028 | In progress | On track |
P51800077422 Mumbai Suburban · MH | Mumbai Suburban MH | 13 Aug 2024 | 31 Dec 2028 | In progress | On track |