Shree Developers
RERA delivery track record · complaints · project delays
NAME:SHREE DEVELOPERS
C62/100
Mixed track record
Tracking 6 projects — 4 delivered, 2 still active. 3 of 6 (50%) ran late by an average of 2 months.
Delivery breakdown
How this builder's 6 tracked projects are split by outcome.
Key numbers
Total projects
6
Active
2
Completed
4
Delayed
3 (50%)
Late or overdue
Avg delay
1.8 mo
Worst: 7 mo
On-time rate
75%
Of completed projects
Extension rate
33%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (6)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
P51700013083 Thane · MH | Thane MH | 14 Sept 2017 | 31 Jan 2020 | Completed | On track |
P51800006487 Mumbai Suburban · MH | Mumbai Suburban MH | 14 Aug 2017 | 31 Dec 2019 | Completed | On track |
P51800005303 Mumbai Suburban · MH | Mumbai Suburban MH | 11 Aug 2017 | 31 Jul 2018 | Overdue | 95 mo overdue |
P51900020641 Mumbai City · MH | Mumbai City MH | 30 Apr 2019 | 1 Sept 2023 | Overdue | 34 mo overdue |
P52000003239 Raigarh · MH | Raigarh MH | 5 Aug 2017 | 31 Dec 2017 | Completed | On track |
P52100003686 Pune · MH | Pune MH | 6 Aug 2017 | 31 Dec 2017 | Completed | 7 mo delay |