Weak track record

Tracking 3 projects — 2 delivered, 1 still active. 2 of 3 (67%) ran late by an average of 6 months.

Delivery breakdown

How this builder's 3 tracked projects are split by outcome.

1 Delivered on time1 Delivered late1 Overdue

Key numbers

Total projects

3

Active

1

Completed

2

Delayed

2 (67%)

Late or overdue

Avg delay

6 mo

Worst: 12 mo

On-time rate

50%

Of completed projects

Extension rate

33%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (3)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
P51800010627
Mumbai Suburban · MH
Mumbai Suburban
MH
31 Aug 201731 Jan 2019Completed12 mo delay
P51800029770
Mumbai Suburban · MH
Mumbai Suburban
MH
29 Jun 202130 Sept 2023CompletedOn track
P51800055072
Mumbai Suburban · MH
Mumbai Suburban
MH
29 Feb 202431 Mar 2026Overdue3 mo overdue