Shri Neelkanth Developers
NAME:SHRI NEELKANTH DEVELOPERS
D38/100
Weak track record
Tracking 3 projects — 2 delivered, 1 still active. 2 of 3 (67%) ran late by an average of 6 months.
Delivery breakdown
How this builder's 3 tracked projects are split by outcome.
Key numbers
Total projects
3
Active
1
Completed
2
Delayed
2 (67%)
Late or overdue
Avg delay
6 mo
Worst: 12 mo
On-time rate
50%
Of completed projects
Extension rate
33%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (3)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
P51800010627 Mumbai Suburban · MH | Mumbai Suburban MH | 31 Aug 2017 | 31 Jan 2019 | Completed | 12 mo delay |
P51800029770 Mumbai Suburban · MH | Mumbai Suburban MH | 29 Jun 2021 | 30 Sept 2023 | Completed | On track |
P51800055072 Mumbai Suburban · MH | Mumbai Suburban MH | 29 Feb 2024 | 31 Mar 2026 | Overdue | 3 mo overdue |