RERA delivery track record · complaints · project delays

NAME:SIDHIVINAYAK CONSTRUCTIONS

Poor track record

Tracking 6 projects — 4 delivered, 2 still active. 3 of 6 (50%) ran late by an average of 18 months.

Delivery breakdown

How this builder's 6 tracked projects are split by outcome.

1 Delivered on time3 Delivered late2 In progress

Key numbers

Total projects

6

Active

2

Completed

4

Delayed

3 (50%)

Late or overdue

Avg delay

18 mo

Worst: 24 mo

On-time rate

25%

Of completed projects

Extension rate

67%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (6)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
P51800002068
Mumbai Suburban · MH
Mumbai Suburban
MH
31 Jul 201731 Dec 2018Completed24 mo delay
P51800003149
Mumbai Suburban · MH
Mumbai Suburban
MH
4 Aug 201731 Dec 2018Completed24 mo delay
P51800008516
Mumbai Suburban · MH
Mumbai Suburban
MH
19 Aug 201731 Dec 2018Completed24 mo delay
P51800033003
Mumbai Suburban · MH
Mumbai Suburban
MH
3 Feb 202219 Aug 2024In progressOn track
P51800046002
Mumbai Suburban · MH
Mumbai Suburban
MH
15 Jun 202231 Mar 2025CompletedOn track
P51800076833
Mumbai Suburban · MH
Mumbai Suburban
MH
28 Jun 202430 Sept 2026In progressOn track