SUDHANSHU INFRASTRUCTURES PRIVATE LIMITED

NAME:SUDHANSHU INFRASTRUCTURES

Poor track record

Tracking 5 projects — 1 delivered, 4 still active. 3 of 5 (60%) ran late by an average of 55 months.

Delivery breakdown

How this builder's 5 tracked projects are split by outcome.

1 Delivered late2 Overdue2 In progress

Key numbers

Total projects

5

Active

4

Completed

1

Delayed

3 (60%)

Late or overdue

Avg delay

54.5 mo

Worst: 54.5 mo

On-time rate

0%

Of completed projects

Extension rate

80%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (5)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
P51800015748
Mumbai Suburban · MH
Mumbai Suburban
MH
22 Mar 201810 Sept 2019Completed55 mo delay
P51800019314
Mumbai Suburban · MH
Mumbai Suburban
MH
23 Jan 201930 Jun 2022Overdue36 mo overdue
P51800024276
Mumbai Suburban · MH
Mumbai Suburban
MH
3 Feb 202030 Dec 2025In progressOn track
P51800027547
Mumbai Suburban · MH
Mumbai Suburban
MH
14 Dec 202030 Jun 2023Overdue3 mo overdue
P51800050455
Mumbai Suburban · MH
Mumbai Suburban
MH
17 Apr 202331 Dec 2026In progressOn track