TATA HOUSING DEVELOPMENT COMPANY LIMITED

RERA delivery track record · complaints · project delays

NAME:TATA HOUSING DEVELOPMENT COMPANY

Good track record

Tracking 3 projects — 1 delivered, 2 still active. 2 of 3 (67%) ran late.

Delivery breakdown

How this builder's 3 tracked projects are split by outcome.

1 Delivered on time2 Overdue

Key numbers

Total projects

3

Active

2

Completed

1

Delayed

2 (67%)

Late or overdue

Avg delay

0 mo

On finished projects

On-time rate

100%

Of completed projects

Extension rate

33%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (3)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
P51900007527
Mumbai Suburban · MH
Mumbai Suburban
MH
17 Aug 201730 Dec 2023Overdue18 mo overdue
P51900007740
Mumbai Suburban · MH
Mumbai Suburban
MH
17 Aug 201730 Dec 2025Overdue6 mo overdue
P51700000308
Thane · MH
Thane
MH
15 Jul 201731 Mar 2018CompletedOn track