United Enterprises

RERA delivery track record · complaints · project delays

NAME:UNITED ENTERPRISES

Weak track record

Tracking 3 projects — 2 delivered, 1 still active. 1 of 3 (33%) ran late by an average of 12 months.

Delivery breakdown

How this builder's 3 tracked projects are split by outcome.

1 Delivered on time1 Delivered late1 In progress

Key numbers

Total projects

3

Active

1

Completed

2

Delayed

1 (33%)

Late or overdue

Avg delay

12 mo

Worst: 24 mo

On-time rate

50%

Of completed projects

Extension rate

33%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (3)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
P51800000556
Mumbai Suburban · MH
Mumbai Suburban
MH
18 Jul 201731 Dec 2019Completed24 mo delay
P51800000645
Mumbai Suburban · MH
Mumbai Suburban
MH
19 Jul 201730 Jun 2019CompletedOn track
P51800047418
Mumbai Suburban · MH
Mumbai Suburban
MH
27 Oct 202231 Dec 2026In progressOn track