V K DEVELOPERS
RERA delivery track record · complaints · project delays
NAME:V K DEVELOPERS
B79/100
Good track record
Tracking 6 projects — 2 delivered, 4 still active. 3 of 6 (50%) ran late.
Delivery breakdown
How this builder's 6 tracked projects are split by outcome.
Key numbers
Total projects
6
Active
4
Completed
2
Delayed
3 (50%)
Late or overdue
Avg delay
0 mo
On finished projects
On-time rate
100%
Of completed projects
Extension rate
17%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (6)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
P51900048871 Mumbai City · MH | Mumbai City MH | 24 Jan 2023 | 30 Dec 2025 | Overdue | 6 mo overdue |
P51900019014 Mumbai City · MH | Mumbai City MH | 28 Dec 2018 | 30 Dec 2023 | Overdue | 30 mo overdue |
P51800015316 Mumbai Suburban · MH | Mumbai Suburban MH | 15 Feb 2018 | 28 Feb 2022 | Completed | On track |
P51800029146 Mumbai Suburban · MH | Mumbai Suburban MH | 29 Apr 2021 | 31 Dec 2024 | Completed | On track |
P51800053621 Mumbai Suburban · MH | Mumbai Suburban MH | 21 Nov 2023 | 15 Mar 2027 | In progress | On track |
RERA-GRG-1183-2022 Gurgaon · HR | Gurgaon HR | 28 Nov 2022 | 30 Apr 2025 | Overdue | 14 mo overdue |