A93/100
Strong track record
Tracking 3 projects — 1 delivered, 2 still active. No delays recorded so far.
Delivery breakdown
How this builder's 3 tracked projects are split by outcome.
Key numbers
Total projects
3
Active
2
Completed
1
Delayed
0 (0%)
Late or overdue
Avg delay
0 mo
On finished projects
On-time rate
100%
Of completed projects
Extension rate
33%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (3)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
P51800045822 Mumbai Suburban · MH | Mumbai Suburban MH | 15 Jun 2022 | 15 Mar 2027 | In progress | On track |
P51800012457 Mumbai Suburban · MH | Mumbai Suburban MH | 1 Sept 2017 | 31 Dec 2019 | Completed | On track |
P51800049808 Mumbai Suburban · MH | Mumbai Suburban MH | 24 Feb 2023 | 31 Dec 2025 | In progress | On track |