KANAKIA LEVELS
P51800000223
Delivered — but late
This project was completed about 24 months after its original promised deadline.
Where this project stands
The journey from RERA registration to completion, in order.
Completed.
Registered with RERA
10 Jul 2017Original promised completion
31 Oct 2019The deadline the builder committed to at registration.
Revised deadline after extensions
30 Oct 2021Pushed back ~24 months across 1 extension.
Marked completed on the portal
Shown as completed on the official registry (no exact date scraped).
Timeline & delay
Key dates and how they compare to what was promised.
10 Jul 2017
When the project was registered with RERA.
31 Oct 2019
The deadline committed to at registration.
30 Oct 2021
After all approved extensions.
—
Handover date, when available.
24 mo delay24 mo
How late the finished project was.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
8
Complaints against the builder
0
Often reported per project on MahaRERA
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 31 Oct 2019 | 30 Oct 2021 | MahaRERA extension (original vs revised completion date) |
About the builder
How this developer has performed across all their tracked projects.
Mixed track record
Tracking 7 projects — 7 delivered, 0 still active. 2 of 7 (29%) ran late by an average of 7 months.
See KANAKIA SPACES REALTY PRIVATE LIMITED's full track record →
Official records
Builder: KANAKIA SPACES REALTY PRIVATE LIMITED (NAME:KANAKIA SPACES REALTY PRIVATE LIMITED)
Data last refreshed 21 Jun 2026.