SHETH BLUE IVY
P51800001407
Under construction
Currently within its planned build window. Watch the deadline and any new extensions.
Where this project stands
The journey from RERA registration to completion, in order.
Approaching the deadline.
Registered with RERA
28 Jul 2017Original promised completion
30 Jun 2023The deadline the builder committed to at registration.
Revised deadline after extensions
28 Nov 2027Pushed back ~53 months across 1 extension.
Today — in progress
About 17 months left until the deadline.
Timeline & delay
Key dates and how they compare to what was promised.
28 Jul 2017
When the project was registered with RERA.
30 Jun 2023
The deadline committed to at registration.
28 Nov 2027
After all approved extensions.
—
Handover date, when available.
On track0 mo
How far past deadline an ongoing project is.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
21
Complaints against the builder
0
Often reported per project on MahaRERA
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 30 Jun 2023 | 28 Nov 2027 | MahaRERA extension (original vs revised completion date) |
About the builder
How this developer has performed across all their tracked projects.
Mixed track record
Tracking 6 projects — 3 delivered, 3 still active. 1 of 6 (17%) ran late by an average of 10 months.
Official records
Builder: Sheth Developers Private Limited (NAME:Sheth Developers Private Limited)
Data last refreshed 21 Jun 2026.