SUN-VISON SOLITAIRE
P51800001637
Delivered — but late
This project was completed about 33 months after its original promised deadline.
Where this project stands
The journey from RERA registration to completion, in order.
Completed.
Registered with RERA
29 Jul 2017Original promised completion
31 Mar 2018The deadline the builder committed to at registration.
Revised deadline after extensions
30 Dec 2020Pushed back ~33 months across 1 extension.
Marked completed on the portal
Shown as completed on the official registry (no exact date scraped).
Timeline & delay
Key dates and how they compare to what was promised.
29 Jul 2017
When the project was registered with RERA.
31 Mar 2018
The deadline committed to at registration.
30 Dec 2020
After all approved extensions.
—
Handover date, when available.
33 mo delay33 mo
How late the finished project was.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
2
Complaints against the builder
0
Often reported per project on MahaRERA
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 31 Mar 2018 | 30 Dec 2020 | MahaRERA extension (original vs revised completion date) |
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 1 project — 1 delivered, 0 still active. 1 of 1 (100%) ran late by an average of 33 months. Limited history — read the project list before drawing conclusions.
Official records
Builder: DHAN INTERNATIONAL PVT LTD (NAME:DHAN INTERNATIONAL PVT LTD)
Data last refreshed 21 Jun 2026.