Rajal

P51800002139

Mumbai Suburban, MaharashtraResidential / Group HousingOverdue

Behind schedule

This project is about 36 months past its latest deadline and is not yet marked completed.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 31 Jul 2017Due 30 Jun 2023

Past deadline by ~36 months.

  1. Registered with RERA

    31 Jul 2017
  2. Original promised completion

    30 Jun 2023

    The deadline the builder committed to at registration.

  3. Today — still not completed

    About 36 months past the latest deadline.

Timeline & delay

Key dates and how they compare to what was promised.

31 Jul 2017

When the project was registered with RERA.

30 Jun 2023

The deadline committed to at registration.

30 Jun 2023

After all approved extensions.

Handover date, when available.

36 mo overdue35.7 mo

How far past deadline an ongoing project is.

0

More extensions can signal execution risk.

On MahaRERA this project's registration status is Ongoing and its completion status is Lapsed. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

2

Complaints against the builder

0

Often reported per project on MahaRERA

About the builder

How this developer has performed across all their tracked projects.

Strong track record

Tracking 4 projects — 3 delivered, 1 still active. 1 of 4 (25%) ran late.

4 projects1 delayed (25%)100% on time

See Nisar Properties Private Limited's full track record →

Official records

View this project on the MahaRERA portal

Builder: Nisar Properties Private Limited (NAME:Nisar Properties Private Limited)

Data last refreshed 21 Jun 2026.